docs: Fixes on inception document and Gantt chart after review with Bavota

git-svn-id: svn+ssh://atelier.inf.usi.ch/home/bevilj/group-1@27 a672b425-5310-4d7a-af5c-997e18724b81
This commit is contained in:
Claudio Maggioni 2018-11-02 12:50:49 +00:00
parent 224b88c682
commit 0af63a49b4
2 changed files with 8 additions and 21 deletions

View File

@ -82,26 +82,13 @@ The CSS team must finish the main CSS for Monday, before 1pm.]]></notes>
<task id="88" name="Speaker Midway Milestone" color="#ff0000" meeting="false" start="2018-11-09" duration="4" complete="0" thirdDate="2018-10-19" thirdDate-constraint="0" expand="true">
<notes><![CDATA[The speaker must prepare the speech for the Midway Milestone day.]]></notes>
</task>
<task id="39" name="Control Pages" color="#ff0000" meeting="false" start="2018-11-10" duration="2" complete="0" thirdDate="2018-11-12" thirdDate-constraint="0" priority="2" expand="true">
<notes><![CDATA[Only for:
Claudio Maggioni
Joey Bevilacqua
Domenico Votta
Marco Tereh
They control if the websites have the problem and will do some tests.]]></notes>
</task>
<task id="67" name="MIDWAY MILESTONE" color="#000000" meeting="true" start="2018-11-12" duration="0" complete="0" thirdDate="2018-10-19" thirdDate-constraint="0" priority="4" expand="true">
<notes><![CDATA[On this day the speaker will present the current status of the project.]]></notes>
</task>
<task id="33" name="Final pages delivery" color="#00cc33" meeting="false" start="2018-11-10" duration="5" complete="0" thirdDate="2018-10-17" thirdDate-constraint="0" priority="4" expand="true">
<task id="33" name="Final pages delivery" color="#00cc33" meeting="false" start="2018-11-10" duration="4" complete="0" thirdDate="2018-10-17" thirdDate-constraint="0" priority="4" expand="true">
<notes><![CDATA[Each Team must deliver the pages left]]></notes>
</task>
<task id="35" name="Final Review" color="#ff0000" meeting="false" start="2018-11-15" duration="4" complete="0" thirdDate="2018-10-17" thirdDate-constraint="0" priority="2" expand="true">
<task id="35" name="Final Review" color="#ff0000" meeting="false" start="2018-11-14" duration="4" complete="0" thirdDate="2018-10-17" thirdDate-constraint="0" priority="2" expand="true">
<notes><![CDATA[Only for:
Claudio Maggioni
@ -114,7 +101,7 @@ Marco Tereh
They control if the websites have the problem and will do some tests.]]></notes>
</task>
<task id="89" name="Teamwork report" color="#8cb6ce" meeting="false" start="2018-11-15" duration="4" complete="0" thirdDate="2018-10-15" thirdDate-constraint="0" expand="true"/>
<task id="89" name="Teamwork report" color="#8cb6ce" meeting="false" start="2018-11-14" duration="4" complete="0" thirdDate="2018-10-15" thirdDate-constraint="0" expand="true"/>
<task id="70" name="FINAL MILESTONE" color="#000000" meeting="true" start="2018-11-19" duration="0" complete="0" thirdDate="2018-10-19" thirdDate-constraint="0" priority="4" expand="true">
<notes><![CDATA[Deliver the final website]]></notes>
</task>

View File

@ -20,8 +20,8 @@ Our website will be divided in these sections:
\paragraph{File system}
A section about navigating the file system, absolute and relative paths,
the \texttt{.} and \texttt{..} shortcuts, symbolic and hard links, and
manipulating (creating, renaming, editing, moving, copying, and deleting)
files.
manipulating (creating, renaming, editing, moving, copying, deleting,
and changing permissions) files.
\paragraph{Commands}
@ -231,7 +231,7 @@ run \texttt{./stop.sh}
\item
Uses two spaces for indentation (tab = 2 spaces);
\item
Put one new line for each tag;
Put one new line for each block tag;
\item
Put no more than 100 chars for each line;
\item
@ -326,8 +326,8 @@ First 3 pages delivery & 05-11 & 09-11 & Contents teams\\
Initial project review & 08-11 & 11-11 & Group management\\
Final pages delivery & 10-11 & 14-11 & Contents teams\\
\textbf{Midway milestone} & 12-11 & & \\
Final review & 15-11 & 18-11 & Group management\\
Teamwork report & 15-11 & 18-11 & Group management\\
Final review & 14-11 & 17-11 & Group management\\
Teamwork report & 14-11 & 17-11 & Group management\\
\textbf{Final milestone} & 19-11 & & \\
\textbf{Final presentation} & 23-11 & &